Komatsu equipment gets the job done
With road repairs to one bridge done and
demolition of another behind it, Manhattan Road
& Bridge is earnestly working on construction
of a new, multipurpose, westbound bridge
on Interstate 244 in Tulsa. The locally based
company began the nearly $64 million project in
late spring and is expected to complete it during
the course of this year and next.
The new bridge’s top deck is designed to
carry four lanes of traffic across the Arkansas
River, with a bottom deck designed for future
rail use, although the rail lines won’t be put in
as part of this project. Pedestrian and bicycle
traffic areas will also be part of the bottom
deck. The new, completed bridge, slated to
be finished in late 2013, will be about 300 feet
longer than its predecessor.
Manhattan Road & Bridge began the
construction phase as it was wrapping up
demolition of the existing bridge, drilling new
piers while taking down the supports for the
previous structure that was built in 1967. The
bridge was considered functionally obsolete,
meaning it could no longer meet traffic demands
of a city with a population of more than 390,000.
Throughout its short history — Manhattan
was formed out of two businesses merging
together — the company has completed some of
Oklahoma’s most recognizable public projects,
including the six miles of reconstruction it did
on Interstate 244 in Tulsa. It also relocated about
six miles of Interstate 40 through downtown
Oklahoma City. Those projects, as well as
several other multimillion-dollar ventures,
helped Manhattan Road & Bridge approach this
Interstate 244 job with confidence it could meet
the scheduled time frame for completion, even
with some unique challenges.
Protecting Route 66
In late spring, Manhattan Road & Bridge
began repairing the surface of the existing
eastbound Interstate 244 bridge. The repairs were
necessary to ensure the bridge stayed in good
working order while the westbound bridge was
demolished and the new one constructed. That
existing bridge currently carries traffic both ways.
“We mainly worked nights and weekends
on the repairs to minimize traffic disruption,”
said Manhattan Senior Vice President Mike
Webb. “That went very well, as did the
demolition, despite facing some challenges
that required us to do some of the work
differently than we normally would.”
Among the challenges of the demolition phases
was protecting the nearby 11th Street Bridge,
which is part of the historic Route 66 and sits
as close as 40 feet to where the old bridge was
in some spots. To lessen the impact, Manhattan
Road & Bridge placed a heavy layer of sand
underneath the Interstate 244 bridge — in the
areas that weren’t over water — to cushion
the impact of debris hitting the ground as it
demolished the bridge.
“We also minimized the impact by taking the
bridge down in smaller chunks,” said General
Superintendent Reed Wood, who’s overseeing
the project and noted an additional challenge
included working next to a refinery with trains
moving in and out and crossing a railroad
bridge in close proximity. “Seismographs were
set up to monitor vibration and movement.
Our processes worked, and we were able to
demolish the bridge without any issues.”
Versatile Komatsu equipment
The demolition began with Manhattan Road
& Bridge removing the deck of the old bridge.
Much of the concrete material was used on
site to build a causeway that allowed crews
to move machinery, personnel and materials
across the Arkansas River.
Manhattan Road & Bridge used a
combination of Komatsu excavators, ranging
in size from a compact PC88 to a PC400LC-8,
equipped with NPK hammers and processing
jaws to break up concrete materials and sort
out and cut rebar. Additional excavators
included a PC228, a PC270 and a PC138.
“Demolition puts a heavy toll on machinery,
but our Komatsu equipment has always
stood up to the challenge and gives us good
productivity, reported Wood. “The hydraulic
excavators have excellent power to run any of
the attachments we put on them, which makes
us appreciate the versatility they offer. We can
hammer, process and dig with one machine,
and that makes a big difference to the bottom
line.”
As Manhattan Road & Bridge took down the
bridge deck, it hauled and placed concrete in
the river to build the causeway, grading it out
with Komatsu D37 and D61 dozers. Komatsu
wheel loaders were used for a variety of tasks,
including moving materials around the site
and loading trucks.
Manhattan Road & Bridge also used JLG
lifting machines for various tasks, including
lifting personnel up to the top of existing
bridge piers to cut structural steel.
“I’d estimate that at times, our workers were
up to 50 feet in the air,” noted Wood. “We used
the JLGs rather than have our workers walk
beams with lifelines tied to them. It made for a
much safer operation. Of course, we also used
the lifts for getting materials into place, so,
like our Komatsu equipment, the JLGs give us
versatility too.”
In addition to using its own equipment,
Manhattan Road & Bridge turned to Kirby-Smith
Machinery for most of its rental machines,
working with Territory Manager Dan Rutz to
acquire the additional pieces. “It’s common for
us to rent pieces that we wouldn’t necessarily
need on every project,” said Webb. “That keeps
our costs down. We’re very pleased with the
service we get from Dan and Kirby-Smith.”
Experienced staff gets the job done
When the new Interstate 244 westbound
bridge is finished, it will be nearly 3,000 feet
long and Manhattan Road & Bridge will
have used approximately 9 million pounds of
structural steel, 6 million pounds of reinforcing
steel and 39,000 cubic yards of concrete. It
will have excavated more than 30,000 yards
of material and built four retaining walls.
The upper deck that carries traffic must be
completed first, within 550 days from the May
13 start date. Additional days are allowed to
complete the lower portion.
Manhattan Road & Bridge will handle
nearly all the work. Webb and Wood estimate
as many as 250 workers will be involved in the
project. Among them are key individuals, such
as Senior Project Manager Richard Davis and
Project Manager John Poole.
“We sub out a few items, such as a large soil
nail wall on the north end of the project, utility
relocation, electrical work and asphalt paving,
but our personnel will do the vast majority of
the project,” said Webb, who noted that MR&B
remains on schedule. “Making a project like
this work involves not only having the proper
equipment to do the job, but having the right
people in place who know how to get a job
done. Our guys certainly have the experience
to do that. We’re confident that we’ll be done
on time and on budget.”